Milestones

  • The Bavarian Government passes a trailblazing resolution to establish a new university in Nuremberg, which, upon overall completion, is to provide up to 6,000 new places of study.

    The concept is drawn up by a Structural Commission comprising eminent experts under the chairmanship of the President of the Technical University of Munich at the time, Prof. Dr. Wolfgang A. Herrmann.

  • In October 2018, the Bavarian Government presents the “Concept for the Foundation of the University of Technology Nuremberg”, drawn up by the Structural Commission, to the Science Council for review.

    In the south of Nuremberg on Brunecker Straße, the State of Bavaria purchases an area covering 37.5 hectares for the new campus university in direct urban surroundings.

  • The year marks the beginning of planning the urban structures and the first building for the location on Brunecker Straße. At the same time, preliminary action is taken to prepare the site – also regarding a protection of species evaluation and developing work of the land plot.

  • With the positive evaluation of the concept by the Science Council early in 2020, the green light is given for the in-depth operative realization of the project, which has advanced at an incredible pace ever since.

    The City of Nuremberg and the State of Bavaria jointly sign a declaration in March 2020, laying down the cornerstones for the urban development agreement to be signed.

    In December 2020, the Bavarian Parliament passes the “Act on the Establishment of the University of Technology Nuremberg”, thus paving the way for the establishment of the new university starting on January 1st, 2021. On the same date, the development regulation comes into force which forms the statutory framework for the first few years.

  • The tenth state-run university in Bavaria has been officially set up on January 1st, 2021. Dr. Markus Zanner is appointed Provost.

    On March 1st, 2021, Prof. Dr. Dr. h.c. mult. Hans Jürgen Prömel takes up office as Founding President.

    In April 2021, the winner design is selected for the structural and urban design framework. It was submitted by the team around Ferdinand Heide Architekten/TOPOS.

    On August 27th, the first groundbreaking ceremony takes place on the construction site on Brunecker Straße.